Most people think shuttering material is only for big contractors. That's not true. If you're building your own house — even just one room's slab — you can rent MS plates, prop jacks and plywood directly from us at Tikkiwal Timbers LLP. No contractor needed as a middleman.
What is Shuttering Material?
Shuttering (also called formwork) is the temporary framework that holds wet concrete in shape until it hardens. Once the concrete sets (usually 7–21 days), the shuttering is removed and reused. For a house slab, you need three main things:
- MS Plates or Plywood — The flat panels that form the underside of the slab
- Prop Jacks — Adjustable steel poles that support the panels from below
- Chali / MS Channel — Horizontal runners that the panels rest on
MS Plate vs Film-Faced Plywood — Which Should I Use?
| MS Plate | Film-Faced Plywood | |
|---|---|---|
| Finish | Good | Mirror smooth |
| Weight | Heavy | Light |
| Reuse | 80–100 times | 25–35 times |
| Available as | Rent & Buy | Buy only |
| Best for | Columns, beams, walls | Slabs, exposed concrete |
How Much Material Do I Need for a Room Slab?
For a 10ft × 12ft room slab (120 sq.ft), you typically need:
- 8–10 Prop Jacks (spaced 1.2m apart)
- 10–12 MS Plates (3ft × 2ft) or equivalent plywood sheets
- 6–8 Chali runners (8ft length)
Not sure? Call us — we'll calculate the exact requirement free of charge.
Worked Example: Slab of a 20 ft × 15 ft Room
Take a room of 20 ft × 15 ft, which is 300 sq ft of slab. A rough way to plan the material is:
- Prop jacks: with props roughly 1.2 m (about 4 ft) apart in both directions, a 20 × 15 ft room needs about 6 × 5 = 30 props, plus a few extra along the edges and for load-bearing spots.
- Panels: 300 sq ft of slab area divided by the area of one 3 ft × 2 ft plate (6 sq ft) gives about 50 plates, plus 5–10% for cuts and edges.
- Chali runners: one line of runners along each prop row, so about 5 rows of 20 ft, in 8 ft lengths.
These are planning figures and the final count depends on slab thickness, span and the material size. Send us the dimensions and we will confirm the exact list. For more cases see how much shuttering material a slab needs.
Safety and Practical Tips for Homeowners
- Place each prop on firm, level ground or a base plate, never on loose bricks or soil.
- Keep props plumb (vertical) and lock the adjusting pin; do not over-extend the threaded portion.
- Fix cross-bracing or runners between props so the whole structure acts as one frame.
- Seal gaps between panels so cement slurry does not leak, and apply shuttering oil before each pour.
- Do not stack the concrete heap in one place during the pour; spread it so the load stays even.
- Leave the shuttering in place until the engineer allows removal; early stripping is a common cause of cracks and sagging.
Common Mistakes to Avoid
- Renting fewer props to save money, which can leave the slab under-supported.
- Ordering material on the day of the pour instead of a few days earlier.
- Mixing bent or damaged props with good ones.
- Removing props one by one early, rather than as the engineer instructs.
For a comparison of panel options, read shuttering material types, or see our shuttering plate rental rates.
How to Rent from Us as an Individual
- Call or WhatsApp +91 98291 68830
- Tell us your city and what you're building (one slab? full house?)
- We confirm material list, rental rate and delivery date
- Pay 50% advance — we deliver to your site within 72 hours
- After the concrete sets, we collect the material and refund your deposit
We serve individual customers across Jaipur, Ahmedabad, Delhi, Noida, Bengaluru, Rajkot, Agra, Udaipur, Gandhidham, Gurugram, Indore, Amritsar, Kota, Lucknow, Ludhiana, Ghaziabad and Mathura. GST invoice provided for all orders.
FAQs
How long should shuttering stay in place after casting?
Side forms can usually come off earlier, but props under a slab stay longer. The exact time depends on the concrete grade, weather and span, so follow your structural engineer's instruction rather than a fixed number of days.
Can I rent only the prop jacks and arrange plywood myself?
Yes. You can rent any combination of props, plates and runners; we will help you match the quantities.
Do I need to buy shuttering oil?
A release agent (shuttering oil) on the panel face helps the panel come off cleanly and extends its life. We can advise on the quantity when you order.
What if I need more material on the day?
Tell us before the pour. If you add an item to the order early, we can include it in the same delivery.